1、SHANGRI-LA HOTELS AND RESORTSPRE 3.CRITICAL PATHPRE 3.1 CONCEPTDBO 180 - 160The critical path is one of the most important tools guiding the departments toward the opening.Correctly filled and subsequently monitored it presents valuable information concerning the exact status the Department is in at
2、 any given time, and if progress is on line.All activities with start and completion date are recorded. The following procedures are all cross referenced with the critical path on Days Before Opening (DBO).关键路径是指导各部门走向开放的最重要工具之一。正确填写并随后进行监测,它提供了有关该部在任何特定时间的确切状态以及进展是否在线的宝贵信息。记录具有开始和完成日期的所有活动。 以下过程都与开盘前几天 (DBO) 上的关键路径交叉引用。HOUSEKEEPING PRE-OPENING GUIDE09/02PAGE 2 OF 2( ROOMS DIVISION )